UCBN Project Status
Project |
Parks Included |
Status |
Aspen Monitoring |
CIRO, CRMO |
Data collection scheduled for CIRO June 2009; Reporting scheduled for completion October 2009 |
Camas Monitoring |
BIHO, NEPE |
Data collection scheduled for May 2009 (NEPE) and June 2009 (BIHO); Reporting scheduled for completion October 2009 |
Natural Resource Condition Assessment |
All UCBN Parks |
Final report due for JODA, LARO, NEPE, and WHMI in February 2009; Field work begins for BIHO, CIRO, CRMO, and HAFO in May 2009 |
Osprey Monitoring |
LARO |
Initial protocol development April 2009; Osprey monitoring data collection scheduled at LARO June-July 2009 |
Pika Inventory |
CRMO |
Analysis, reporting, and close-out scheduled for completion by October 2009; Participation in 4-park NRPP project ongoing 2009 |
Photomonitoring (targeted projects) |
NEPE, WHMI |
Weippe Prairie photomonitoring May 2009 (NEPE); Doan Creek restoration photomonitoring June 2009 (WHMI) |
Integrated Riparian Monitoring |
BIHO, CIRO, JODA, NEPE, WHMI |
Initial protocol development July-August, 2009 |
Sagebrush-steppe Vegetation Monitoring |
CRMO, JODA, LARO |
Revised protocol scheduled for completion March 2009; Field work scheduled for May-June 2009 |
Statistical Assisstance |
All UCBN Parks |
Multi-Network task agreement funded for continued assistance in FY09 |
Vegetation Mapping |
CIRO, CRMO, HAFO, JODA, LARO |
Plot data collection April-July 2009 (CIRO); Completion reports due for CRMO and HAFO; Photo interpretation work planned for JODA; Preliminary maps in progress for LARO |
Water Quality Monitoring |
BIHO, CIRO, WHMI |
Water chemistry and macroinvertebrate data collection at BIHO and CIRO, and water chemistry data collection at WHMI; Field work begins May-June 2009 |